Case Study: 480m3 concrete pour - LG Electronics Factory, Newport
The brief
We were tasked with mixing and delivering 480m3 of concrete for the LG Electronics factory in Newport, South Wales.
The solution
This was a project that we completed in three stages. We put our 32m boom pump to good use along with 180m of additional line in order to deliver concrete to the site in three 160m3 batches. Fellow members of The LGW Group, Prodeck Fixing and Nationwide Concreting, were also involved in ensuring the success of the project, providing steel decking and concrete finishing services respectively.
Thanks to our high quality concrete mix and concrete pump, we managed to complete the job with ease and efficiency - finishing the job on time and on budget!
Do you require commercial concrete or a concrete pump for your project? You can rely on us for an efficient concrete delivery service! Get in touch today on 0117 958 2090.